Research Notes
Minyari Dome's edge rests on its position in Western Australia's Paterson Province, about 35 kilometres from the Telfer gold-copper mine owned by Greatland Resources, which wholly owns that mine, its infrastructure and Havieron after consolidating 100 percent ownership of these in December 2024, where the processing of Havieron ore is intended, and on the option to remain stand-alone that Antipa Minerals maintains as its base case while assessing third-party processing pathways in parallel that may deliver greater risk-weighted value to shareholders.
Simple, non-refractory metallurgy allows a standard Carbon-in-Leach processing plant with an estimated 90 percent gold recovery. Antipa Minerals chose a configuration using conventional carbon-in-leach production of gold doré, followed by flotation of the primary ore residue to produce a separate copper concentrate, after assessing five processing options and their potential effects on capital efficiency, operating costs and the economics of the project.
The pre-feasibility study Antipa Minerals expects in November following extensive scheduling and processing optimisation work is the dated milestone that could change the Minyari Dome Project's growth trajectory, given its resource of approximately 2.5 million ounces of gold, equivalent to 3.2 million ounces that include associated metals.
The 2026 Phase 1 drilling campaign completed 330 holes totalling 42,248m by October 15, and results for 314 holes covered 37,225m. Drilling at Tim's Dome extended the mineralised footprint, reaching approximately 2.2km. Fiama North drilling extended gold-copper mineralisation to approximately 160m along strike and 200m below surface.
The October 2024 scoping study is the turn that moved the Minyari Dome Project toward a stand-alone operation that mines and processes gold, an outcome the company announced that month alongside the key results of its scoping study update. At the Minyari deposit during 2021, mineralisation was discovered immediately east and west, and both up plunge to the southeast and down plunge to the northwest.
The Minyari Project combined Mineral Resource now contains 2.9 million ounces of gold, 91,000 tonnes of copper, 880,000 ounces of silver and 13,000 tonnes of cobalt. In September Antipa selected a processing route that produces gold doré through carbon-in-leach and then floats the primary ore residue into a separate copper concentrate. Antipa expects a pre-feasibility study for the Minyari Dome gold-copper project in November, following extensive mine scheduling and processing optimisation work.
The $306 million in pre-production capital that Antipa forecasts for Minyari Dome, including $90 million for pre-production mining, could impair the project's path to construction because the company finished the September quarter with $28 million in cash, holds no debt, and spent roughly $11.5 million on exploration, funding its work entirely from that balance. A committed debt facility or a third-party funding pathway would indicate that this exposure is being reduced.
With the pre-feasibility study approaching completion, Antipa's next priorities include progressing environmental, regulatory, and financing-related activities for the Minyari Dome Project. At an assumed gold price of $3,000 an ounce, the project shows a post-tax net present value of $598 million for a +10-year, 3-million-tonne-per-annum operation. At an assumed gold price of $4,000 an ounce, the net present value and internal rate of return increase to $1.2 billion and 79 percent, respectively.