B-Act manages, advises on and oversees construction projects as contract engineer and contract administrator.
What is the investment case, and what must be true for it to hold?
B-Act’s gross backlog of PLN 223.7 million as of August 11, 2026, with PLN 144.0 million still to be invoiced, creates a route to stronger results, but second-quarter 2026 sales revenue of PLN 5.9 million and net profit of PLN 175,000, down from PLN 11.6 million and PLN 1.7 million a year earlier, make delivering and invoicing that work the central condition for the investment case.
B-Act expects financial results to improve in subsequent quarters as current contracts complete and deliver key stages.
Which risks could break the thesis, and what would warn of them?
The key risk is that delayed delivery or settlement of B-Act's contract backlog prolongs its weak financial results. Second-quarter 2026 sales revenue fell to PLN 5.9 million from PLN 11.6 million a year earlier and net profit dropped to PLN 175,000 from PLN 1.7 million, a sharp decline that is the observable warning sign. Against that, a gross backlog of PLN 223.7 million as of August 11, 2026, including PLN 144.0 million still to be invoiced, is a substantial counter-indicator but not proof of recovery.
In June 2026 B-Act signed two large contracts: one with GDDKiA with a gross value of PLN 35.6 million and one with the Szczecin and Świnoujście port worth up to PLN 23.8 million. The company expects financial results to improve in subsequent quarters as key stages of its current contracts are settled and delivered.
What does the product do for its buyer, and how is it delivered?
B-Act represents investors throughout construction projects by serving as contract engineer, investor's supervisor, or substitute investor, delivering technical, financial, and legal support across the project. It tracks construction progress, quality, costs, and contractual deadlines with IT tools, and administers the contracts that oversee how the project is executed.
WS Construction Management provides project coordination in the roles of substitute investor, project manager, or contract engineer, and it represents investors in the investment process.