Business Cycle
Peru's electricity distribution sub-sector is in an expansion phase: production rose from 53,990 GWh in 2021 to 61,244 GWh in 2025, 2.0% above December 2024, effective capacity reached 14,388 MW at December 2025, 4.3% above the 13,792 MW of December 2024, and average marginal cost fell to 30.3 US$/MWh in 2024 and 28.5 US$/MWh in 2025 with greater water availability and less thermal generation.
Hidrandina announced a 2025-2028 investment plan for its La Libertad Norte business unit covering 33 strategic works with a total investment of S/191,649,323 for more than 192,655 families. The portfolio comprises 2 completed works, 4 in execution and 27 to execute, responding to urban growth, economic dynamism and sustained growth in energy demand.
Growth Drivers
Demand growth in Hidrandina's concession could raise its energy sales because that growth is driving a S/521.5 million works plan whose Huaraz business unit has 29 works still to execute. Hidrandina announced the 2025-2028 investment plan for its whole concession area, aimed at works that improve the quality and continuity of electricity service for 1.2 million families in La Libertad, Ancash and southern Cajamarca. The Huaraz business unit's portfolio also includes 2 works about to start, responding to urban growth, economic dynamism and sustained growth in energy demand in the zone.
Pluz's physical energy sales to end customers totaled 9,197 GWh at December 2025, 3.1% (+277 GWh) above December 2024.
Market Outlook
Grupo Distriluz, which includes Hidrandina, loses S/143 million a year from the VAD reset, more than Electro Oriente's S/50 million, in a segment where growth depends on demand volume rather than price. The new VAD in force from 1 November to 31 October 2027 reduces state distribution companies' tariff revenue by 4.5%. The same reset cuts S/18 million a year from Electro Ucayali and S/20 million a year from SEAL, and Hidrandina operates in Ancash, La Libertad and part of Cajamarca.
Peru's electricity production rose from 53,990 GWh in 2021 to 61,244 GWh in 2025, 2.0% above December 2024. For companies in the regulated segment, growth also depends on operating efficiency.
Risk Factors
Distribution tariffs come from a VAD fixing held once every four years, so a four-year regulatory reset can cut Hidrandina's revenue through Grupo Distriluz. The new VAD will remove S/143 million a year from the group, nearly three times Electro Oriente's S/50 million, against S/20 million for SEAL.
Peru's electricity sector depends on the country's hydrological conditions and on gas supply, and it is exposed to climate effects on energy demand. Hydropower supplied 53.4% and thermal generation 36.6% of Peru's electricity production, 90.0% combined.