Kogeneracja supplies district heating as hot water from high-efficiency cogeneration for houses, commercial, public, and industrial buildings.
Currently Offered
Research Notes
A March 1974 decision converted the Czechnica Power Plant into a combined heat and power plant supplying Wrocław with heat, turning the electricity-only station into the city's heat source; on 2 November 1981 the Czechnica Combined Heat and Power Plant began deliveries to Wrocław.
In 2010, the thermal assets of the former TERM-Hydral plant, which provides district heating to Wrocław's Psie Pole area, were acquired. In 2014, a unit with 2.67 MW of electric capacity and 2.75 MW of thermal capacity was built at the Zawidawie Combined Heat and Power Plant.
In 2017, PGE acquired EDF's Polish assets and proposed a new combined-cycle unit at the existing Siechnice site to replace the coal units. In May 2025, the replacement gas-fired unit was commissioned.
Regulation and fuel carry the district heating service's earnings risk: the heat pricing mechanism rests on a tariff regulation from 1998 that no longer reflects current realities, and in 2023 district heat producers posted a PLN 5.12 billion loss with fuel costs at PLN 20.1 billion, over double the 2013 figure, so an adverse tariff decision or a fuel-price rise moves the margin before demand does.
In May 2025 the replacement gas-fired unit was commissioned, and a new combined-cycle unit was proposed for the existing Siechnice site to replace the coal units.